Active
Progress
70.06%
Handover
Escrow
#12302366820002

PIER 8

#2380 · PIER 8 REAL ESTATE DEVELOPMENT L.L.C · Marsa Dubai · 341 units

declared value 365.0M AED data last checked 12 Sept 2026

Freehold mixed residential / hotel development in Dubai Marina. It is designed and constructed as 2B+G+2P+46. The tower is designed to be built out of concrete structure and block with internal and external finishes.

Construction progress

70.06% of construction complete · last inspected by DLD 14 Feb 2024

on pace with the planned timeline

last DLD inspection was 2.6 years ago — this figure may no longer reflect the site's actual progress

today
inspected 14 Feb 2024
start 10 Apr 2022 est. finish 8 Mar 2026