photo: peacehomesdevelopment.comUnder constructionPeace Lagoons by Peace Homes
DLD developer no. 1745 · PEACE HOMES DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 10 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 77.52 | 834 | 1,065,270 | 13,742 | 1,277 |
| 10 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 75.04 | 808 | 1,144,539.36 | 15,252 | 1,417 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 122.09 | 1,314 | 1,543,192.3 | 12,640 | 1,174 |
| 24 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 75.77 | 816 | 1,186,522 | 15,660 | 1,455 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 74.46 | 801 | 1,104,486 | 14,833 | 1,378 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.32 | 778 | 971,666 | 13,436 | 1,248 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 115.76 | 1,246 | 1,431,061 | 12,362 | 1,148 |
| 17 Sept 2026 | Sales | Off-plan | Flat · Studio | 37.64 | 405 | 603,240 | 16,027 | 1,489 |
| 16 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.32 | 778 | 983,812 | 13,604 | 1,264 |
| 11 Sept 2026 | Sales | Off-plan | Flat · Studio | 36.87 | 397 | 612,498 | 16,612 | 1,543 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 74.45 | 801 | 1,151,231 | 15,463 | 1,437 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 74.58 | 803 | 1,136,425.29 | 15,238 | 1,416 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 74.45 | 801 | 1,250,000 | 16,790 | 1,560 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 77.55 | 835 | 1,216,353 | 15,685 | 1,457 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 74.58 | 803 | 1,232,415 | 16,525 | 1,535 |
Peace Lagoons by Peace Homes: common questions
Is Peace Lagoons by Peace Homes delayed?
It is behind plan. Construction was 4.16% complete at the last DLD inspection on 21 October 2026, while its registered timeline (planned completion 30 September 2028) would expect about 51% by then.
When is the handover of Peace Lagoons by Peace Homes?
The planned completion date registered with Dubai Land Department is 30 September 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Peace Lagoons by Peace Homes is built?
Construction was 4.16% complete at the last DLD inspection on 21 October 2026, as published by Dubai Land Department.
Where is Peace Lagoons by Peace Homes located?
Peace Lagoons by Peace Homes is in Dubai Land Residence Complex, Dubai.
Who is the developer of Peace Lagoons by Peace Homes?
Peace Lagoons by Peace Homes is developed by PEACE HOMES DEVELOPMENT L.L.C (DLD developer no. 1745). It is registered with Dubai Land Department as project no. 3146.
Does Peace Lagoons by Peace Homes have an escrow account?
Yes. Dubai Land Department open data lists escrow account 01434279157. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Peace Lagoons by Peace Homes?
The most recent sale registered with Dubai Land Department was on 10 October 2026 for AED 1,065,270. Across the 80 recorded sales, the average was AED 1,509 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.