Palm Jebel Ali - Frond Pphoto: palmjebelali.aeActive
Progress
34.65%
Handover
~ Sept 2027
Escrow
#0205839681305

Palm Jebel Ali - Frond P

#2590 · THE PALM - JEBEL ALI CO. (L.L.C) · Palm Jabal Ali

data last checked 17 Jul 2026

Construction progress

34.65% of construction complete · last inspected by DLD 4 Aug 2026

≈37 pts behind the planned pace as of the last inspection

today
inspected 4 Aug 2026
start 13 Sept 2023 est. finish 29 Sept 2027