Palm Jebel Ali - Frond Ophoto: palmjebelali.aeActive
Progress
55.7%
Handover
~ Sept 2027
Escrow
#0205839681303

Palm Jebel Ali - Frond O

#2592 · THE PALM - JEBEL ALI CO. (L.L.C) · Palm Jabal Ali

data last checked 17 Jul 2026

Construction progress

55.7% of construction complete · last inspected by DLD 4 Aug 2026

on pace — ≈16 pts behind the plan as of the last inspection

today
inspected 4 Aug 2026
start 13 Sept 2023 est. finish 29 Sept 2027