photo: palmjebelali.aeUnder constructionPalm Jebel Ali - Frond N
DLD developer no. 104 · THE PALM - JEBEL ALI CO. (L.L.C)
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Sales | Ready | Commercial | 685.11 | 7,374 | 10,239,250 | 14,945 | 1,388 |
| 2 Oct 2026 | Gifts | Ready | Commercial | 703.23 | 7,569 | 21,500,018.98 | 30,573 | 2,840 |
| 2 Oct 2026 | Gifts | Ready | Commercial | 685.11 | 7,374 | 21,300,023.64 | 31,090 | 2,888 |
| 26 Aug 2026 | Sales | Ready | Commercial | 685.11 | 7,374 | 22,300,000 | 32,550 | 3,024 |
| 2 Aug 2026 | Sales | Ready | Commercial | 703.23 | 7,569 | 10,597,299.16 | 15,069 | 1,400 |
| 31 Jul 2026 | Gifts | Ready | Commercial | 703.23 | 7,569 | 7,100,430.04 | 10,097 | 938 |
| 31 Jul 2026 | Gifts | Ready | Commercial | 703.23 | 7,569 | 3,497,019.81 | 4,973 | 462 |
| 25 Jun 2026 | Gifts | Ready | Commercial | 703.14 | 7,569 | 23,000,007.22 | 32,710 | 3,039 |
| 21 May 2026 | Gifts | Ready | Commercial | 703.23 | 7,569 | 20,004,435 | 28,447 | 2,643 |
| 7 May 2026 | Gifts | Ready | Commercial | 703.23 | 7,569 | 20,004,435 | 28,447 | 2,643 |
| 17 Apr 2026 | Gifts | Ready | Commercial | 703.14 | 7,569 | 20,750,002.65 | 29,510 | 2,742 |
| 3 Apr 2026 | Sales | Ready | Commercial | 685.11 | 7,374 | 21,300,000 | 31,090 | 2,888 |
| 1 Apr 2026 | Sales | Ready | Commercial | 1,247.39 | 13,427 | 37,200,000 | 29,822 | 2,771 |
| 6 Mar 2026 | Sales | Ready | Commercial | 685.11 | 7,374 | 21,850,000 | 31,893 | 2,963 |
| 16 Feb 2026 | Sales | Ready | Commercial | 685.12 | 7,375 | 22,000,000 | 32,111 | 2,983 |
Palm Jebel Ali - Frond N: common questions
Is Palm Jebel Ali - Frond N delayed?
Not by DLD figures. Construction was 47.1% complete at the last DLD inspection on 5 August 2026, in line with or ahead of its registered timeline (about 71% expected by then, planned completion 8 October 2027).
When is the handover of Palm Jebel Ali - Frond N?
The planned completion date registered with Dubai Land Department is 8 October 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Palm Jebel Ali - Frond N is built?
Construction was 47.1% complete at the last DLD inspection on 5 August 2026, as published by Dubai Land Department.
Where is Palm Jebel Ali - Frond N located?
Palm Jebel Ali - Frond N is in Palm Jabal Ali, Dubai.
Who is the developer of Palm Jebel Ali - Frond N?
Palm Jebel Ali - Frond N is developed by THE PALM - JEBEL ALI CO. (L.L.C) (DLD developer no. 104). It is registered with Dubai Land Department as project no. 2593.
Does Palm Jebel Ali - Frond N have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205839681310. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Palm Jebel Ali - Frond N?
The most recent sale registered with Dubai Land Department was on 26 October 2026 for AED 10,239,250. Across the 10 recorded sales, the average was AED 2,587 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.