Palm Jebel Ali - Frond Kphoto: palmjebelali.aeActive
Progress
47.91%
Handover
~ Dec 2027
Escrow
#0205839681316

Palm Jebel Ali - Frond K

#2596 · THE PALM - JEBEL ALI CO. (L.L.C) · Palm Jabal Ali

data last checked 17 Jul 2026

Construction progress

47.91% of construction complete · last inspected by DLD 5 Aug 2026

on pace — ≈19 pts behind the plan as of the last inspection

today
inspected 5 Aug 2026
start 2 Dec 2023 est. finish 1 Dec 2027