Palatium Residencesphoto: ahmadyardevelopments.comActive
Progress
65.66%
Handover
Escrow
#1011226040086002

Palatium Residences

#3065 · AHMADYAR REAL ESTATE DEVELOPMENT L.L.C · Al Barsha South Fourth · 151 units

declared value 68.5M AED data last checked 12 Sept 2026

G+4P+12F+R

Construction progress

65.66% of construction complete · last inspected by DLD 19 Jun 2026

overdue — planned finish was 31 Mar 2026, still at 65.66%

today
inspected 19 Jun 2026
start 31 May 2024 est. finish 31 Mar 2026