Palace Residences Hillside Aphoto: emaar.comActive
Progress
7.87%
Handover
~ Jun 2029
Escrow
#9009223791259015

Palace Residences Hillside A

#4015 · DUBAI HILLS ESTATE L.L.C · Hadaeq Sheikh Mohammed Bin Rashid

More from Emaar
data last checked 17 Jul 2026

Construction progress

7.87% of construction complete · last inspected by DLD 5 May 2026

on pace — ≈8 pts behind the plan as of the last inspection

today
inspected 5 May 2026
start 30 Sept 2025 est. finish 30 Jun 2029