Orisephoto: orisebeyonddubai.comUnder construction

Orise

DLD project no. 3425 · Madinat Dubai Almelaheyah

Progress
17.64%
DLD inspected 7 Oct 2026
Handover
~ Nov 2027
Est. finish 30 Nov 2027
Escrow
#0205902663702
Registered escrow account
Google rating
3.0 ★
10 reviews

Developer: Orise Residences Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
17.64% of construction complete · last inspected by DLD 7 Oct 2026

≈41 pts behind the planned pace as of the last inspection

today
inspected 7 Oct 2026
start 28 Feb 2025 est. finish 30 Nov 2027
Google · this project
3.0
10 reviews

Location

Orise: common questions

Is Orise delayed?

It is behind plan. Construction was 17.64% complete at the last DLD inspection on 7 October 2026, while its registered timeline (planned completion 30 November 2027) would expect about 58% by then.

When is the handover of Orise?

The planned completion date registered with Dubai Land Department is 30 November 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Orise is built?

Construction was 17.64% complete at the last DLD inspection on 7 October 2026, as published by Dubai Land Department.

Where is Orise located?

Orise is in Madinat Dubai Almelaheyah, Dubai.

Who is the developer of Orise?

Orise is developed by Orise Residences Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3425.

Does Orise have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205902663702. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Orise?

The most recent sale registered with Dubai Land Department was on 16 September 2026 for AED 5,437,000. Across the 3 recorded sales, the average was AED 2,955 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.