Under construction

Opulent Residences

DLD project no. 2887 · Burj Khalifa

Progress
8.49%
DLD inspected 27 Jul 2026
Handover
~ Dec 2027
Est. finish 31 Dec 2027
Escrow
#0205858077509
Registered escrow account
Google rating
—

Developer: East & West Properties L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
8.49% of construction complete · last inspected by DLD 27 Jul 2026

≈56 pts behind the planned pace as of the last inspection

today
inspected 27 Jul 2026
start 1 Jan 2024 est. finish 31 Dec 2027
Google · this project
0 reviews

Opulent Residences: common questions

Is Opulent Residences delayed?

It is behind plan. Construction was 8.49% complete at the last DLD inspection on 27 July 2026, while its registered timeline (planned completion 31 December 2027) would expect about 64% by then.

When is the handover of Opulent Residences?

The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Opulent Residences is built?

Construction was 8.49% complete at the last DLD inspection on 27 July 2026, as published by Dubai Land Department.

Where is Opulent Residences located?

Opulent Residences is in Burj Khalifa, Dubai.

Who is the developer of Opulent Residences?

Opulent Residences is developed by East & West Properties L.L.C. It is registered with Dubai Land Department as project no. 2887.

Does Opulent Residences have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205858077509. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.