photo: ellingtonproperties.comUnder constructionDeveloper: Dutco Ellington Canal Front Real Estate L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Ellington →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 88.9 | 957 | 2,300,000 | 25,872 | 2,404 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 220.96 | 2,378 | 6,600,000 | 29,870 | 2,775 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 97.13 | 1,045 | 2,837,828 | 29,217 | 2,714 |
| 16 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 156.29 | 1,682 | 4,650,828 | 29,758 | 2,765 |
| 16 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 156.6 | 1,686 | 4,536,828 | 28,971 | 2,691 |
| 4 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 97.13 | 1,045 | 3,222,828 | 33,181 | 3,083 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 165.39 | 1,780 | 4,694,828 | 28,386 | 2,637 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 164.97 | 1,776 | 5,516,828 | 33,441 | 3,107 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 134.37 | 1,446 | 3,515,828 | 26,165 | 2,431 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 134.75 | 1,450 | 3,831,828 | 28,437 | 2,642 |
| 3 Aug 2026 | Sales | Off-plan | Flat · Studio | 45.3 | 488 | 1,565,828 | 34,566 | 3,211 |
| 31 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 165.41 | 1,780 | 4,342,828 | 26,255 | 2,439 |
| 31 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 88.89 | 957 | 2,162,500 | 24,328 | 2,260 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 137.33 | 1,478 | 3,606,828 | 26,264 | 2,440 |
| 20 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 111.2 | 1,197 | 2,901,828 | 26,096 | 2,424 |
ONE RIVER POINT: common questions
Is ONE RIVER POINT delayed?
It is behind plan. Construction was 35.43% complete at the last DLD inspection on 21 July 2026, while its registered timeline (planned completion 9 June 2027) would expect about 76% by then.
When is the handover of ONE RIVER POINT?
The planned completion date registered with Dubai Land Department is 9 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of ONE RIVER POINT is built?
Construction was 35.43% complete at the last DLD inspection on 21 July 2026, as published by Dubai Land Department.
Where is ONE RIVER POINT located?
ONE RIVER POINT is in Business Bay, Dubai.
Who is the developer of ONE RIVER POINT?
ONE RIVER POINT is developed by Dutco Ellington Canal Front Real Estate L.L.C. It is registered with Dubai Land Department as project no. 2929.
Does ONE RIVER POINT have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205856303604. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in ONE RIVER POINT?
The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 2,300,000. Across the 85 recorded sales, the average was AED 2,691 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.