Active
Progress
68.7%
Handover
Escrow
#12711866920002

One Crescent

#2567 · A H S PALM DEVELOPMENT L.L.C · Palm Jumeirah · 25 units

escrow #12711866920002 declared value 176.0M AED

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

Residential Building (B+G+9+R).The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

68.7% of construction complete · last inspected by DLD 3 Apr 2026

overdue — planned finish was 1 Mar 2026, still at 68.7%

today
inspected 3 Apr 2026
start 15 May 2023 est. finish 1 Mar 2026