ONAYA RESIDENCES By Kayaphoto: kayadevelopers.comDelayed 4 mo.

ONAYA RESIDENCES By Kaya

DLD project no. 3565 · Al Satwa · 41 units

Progress
37.72%
DLD inspected 19 Feb 2026
Handover
Overdue
Planned finish 27 Jun 2026
Escrow
#3538470053602
Registered escrow account
Google rating
—

DLD developer no. 2223 · KAYA PROPERTIES L.L.C

Data last checked 29 Oct 2026

declared value 23.2M AED

G+2P+8F+R , Residential-Apartment.The project designed to have a concrete structure and block with internal and external finishes.

DLDConstruction inspection
37.72% of construction complete · last inspected by DLD 19 Feb 2026

≈40 pts behind the planned pace as of the last inspection

today
inspected 19 Feb 2026
start 28 Nov 2024 est. finish 27 Jun 2026

Location

ONAYA RESIDENCES By Kaya: common questions

Is ONAYA RESIDENCES By Kaya delayed?

It is behind plan. Construction was 37.72% complete at the last DLD inspection on 19 February 2026, while its registered timeline (planned completion 27 June 2026) would expect about 78% by then.

When is the handover of ONAYA RESIDENCES By Kaya?

The planned completion date registered with Dubai Land Department is 27 June 2026. Handover usually follows completion; the developer confirms the exact date.

How much of ONAYA RESIDENCES By Kaya is built?

Construction was 37.72% complete at the last DLD inspection on 19 February 2026, as published by Dubai Land Department.

Where is ONAYA RESIDENCES By Kaya located?

ONAYA RESIDENCES By Kaya is in Al Satwa, Dubai.

Who is the developer of ONAYA RESIDENCES By Kaya?

ONAYA RESIDENCES By Kaya is developed by KAYA PROPERTIES L.L.C (DLD developer no. 2223). It is registered with Dubai Land Department as project no. 3565, with 41 units.

Does ONAYA RESIDENCES By Kaya have an escrow account?

Yes. Dubai Land Department open data lists escrow account 3538470053602. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.