photo: nshama.aeUnder constructionDLD developer no. 1162 · NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from nshama →No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 186.76 | 2,010 | 2,521,888 | 13,503 | 1,255 |
| 1 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 147.03 | 1,583 | 2,527,888 | 17,193 | 1,597 |
| 20 Aug 2026 | Sales | Off-plan | Flat · 3 B/R | 147.03 | 1,583 | 2,507,888 | 17,057 | 1,585 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 146.97 | 1,582 | 1,813,888 | 12,342 | 1,147 |
| 7 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 125.49 | 1,351 | 1,641,888 | 13,084 | 1,216 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 147.03 | 1,583 | 2,517,888 | 17,125 | 1,591 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 60.11 | 647 | 1,067,888 | 17,766 | 1,650 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 59.94 | 645 | 1,024,888 | 17,099 | 1,589 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 100.05 | 1,077 | 1,588,888 | 15,881 | 1,475 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 143.59 | 1,546 | 2,427,888 | 16,908 | 1,571 |
| 10 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 147.03 | 1,583 | 2,497,888 | 16,989 | 1,578 |
| 28 Jan 2026 | Sales | Off-plan | Flat · 2 B/R | 88.91 | 957 | 1,405,888 | 15,812 | 1,469 |
| 27 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 78.01 | 840 | 1,191,888 | 15,279 | 1,419 |
| 25 Jan 2026 | Sales | Off-plan | Flat · 3 B/R | 143.59 | 1,546 | 2,427,888 | 16,908 | 1,571 |
| 18 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 78.36 | 843 | 1,087,888 | 13,883 | 1,290 |
Odessa: common questions
Is Odessa delayed?
It is behind plan. Construction was 8.01% complete at the last DLD inspection on 13 August 2026, while its registered timeline (planned completion 30 December 2027) would expect about 41% by then.
When is the handover of Odessa?
The planned completion date registered with Dubai Land Department is 30 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Odessa is built?
Construction was 8.01% complete at the last DLD inspection on 13 August 2026, as published by Dubai Land Department.
Where is Odessa located?
Odessa is in Al Yelayiss 2, Dubai.
Who is the developer of Odessa?
Odessa is developed by NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C (DLD developer no. 1162). It is registered with Dubai Land Department as project no. 3450.
Does Odessa have an escrow account?
Yes. Dubai Land Department open data lists escrow account 4031224702173086. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Odessa?
The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 2,521,888. Across the 18 recorded sales, the average was AED 1,469 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.