photo: missoni.comUnder constructionOCTA ISLE Interiors by MISSONI
Developer: Octa Di Development Co. L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 18 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 95.28 | 1,026 | 2,852,899 | 29,942 | 2,782 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 121.87 | 1,312 | 3,626,721 | 29,759 | 2,765 |
| 6 May 2026 | Sales | Off-plan | Flat · 2 B/R | 95.27 | 1,025 | 2,536,336 | 26,623 | 2,473 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 125.95 | 1,356 | 2,580,093 | 20,485 | 1,903 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.28 | 1,026 | 2,308,692 | 24,231 | 2,251 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 5 B/R | 330.07 | 3,553 | 9,200,000 | 27,873 | 2,589 |
| 26 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.28 | 1,026 | 2,469,999 | 25,924 | 2,408 |
| 18 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.28 | 1,026 | 2,592,443 | 27,209 | 2,528 |
| 18 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 121.86 | 1,312 | 3,617,888 | 29,689 | 2,758 |
| 18 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.29 | 1,026 | 2,513,454 | 26,377 | 2,450 |
| 17 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.21 | 1,025 | 2,293,332 | 24,087 | 2,238 |
| 17 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 127.29 | 1,370 | 3,575,311 | 28,088 | 2,609 |
| 9 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.28 | 1,026 | 2,966,888 | 31,139 | 2,893 |
| 9 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 95.21 | 1,025 | 3,093,221 | 32,488 | 3,018 |
| 19 Feb 2026 | Sales | Off-plan | Flat · 4 B/R | 362.78 | 3,905 | 4,500,000 | 12,404 | 1,152 |
OCTA ISLE Interiors by MISSONI: common questions
Is OCTA ISLE Interiors by MISSONI delayed?
It is behind plan. Construction was 6.24% complete at the last DLD inspection on 1 September 2026, while its registered timeline (planned completion 30 September 2027) would expect about 50% by then.
When is the handover of OCTA ISLE Interiors by MISSONI?
The planned completion date registered with Dubai Land Department is 30 September 2027. Handover usually follows completion; the developer confirms the exact date.
How much of OCTA ISLE Interiors by MISSONI is built?
Construction was 6.24% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.
Where is OCTA ISLE Interiors by MISSONI located?
OCTA ISLE Interiors by MISSONI is in Palm Deira, Dubai.
Who is the developer of OCTA ISLE Interiors by MISSONI?
OCTA ISLE Interiors by MISSONI is developed by Octa Di Development Co. L.L.C. It is registered with Dubai Land Department as project no. 3793.
Does OCTA ISLE Interiors by MISSONI have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205922398102. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in OCTA ISLE Interiors by MISSONI?
The most recent sale registered with Dubai Land Department was on 18 August 2026 for AED 2,852,899. Across the 26 recorded sales, the average was AED 2,348 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.