OCTA ISLE Interiors by MISSONIphoto: missoni.comActive
Progress
6.24%
Handover
~ Sept 2027
Escrow
#0205922398102

OCTA ISLE Interiors by MISSONI

#3793 · Octa Di Development Co. L.L.C · Palm Deira

data last checked 17 Jul 2026

Construction progress

6.24% of construction complete · last inspected by DLD 1 Sept 2026

≈44 pts behind the planned pace as of the last inspection

today
inspected 1 Sept 2026
start 1 Aug 2025 est. finish 30 Sept 2027