Oasiz 2 by Danubephoto: danubeproperties.comActive
Progress
31%
Handover
~ Nov 2027
Escrow
#011181475010

Oasiz 2 by Danube

#3260 · DANUBE PROPERTIES DEVELOPMENT L.L.C · Silicon Oasis

More from Danube
data last checked 17 Jul 2026

Construction progress

31% of construction complete · last inspected by DLD 29 Jul 2026

on pace — ≈24 pts behind the plan as of the last inspection

today
inspected 29 Jul 2026
start 1 Dec 2024 est. finish 30 Nov 2027
Google · this project
4.4
14 reviews