OASIS RESIDENCESphoto: hzdevelopment.aeActive
Progress
35.25%
Handover
~ Jul 2027
Escrow
#3717370312519

OASIS RESIDENCES

#3726 · AL HELAL AL ZAHABY REAL ESTATE DEVELOPMENT L.L.C · Dubai South

data last checked 17 Jul 2026

Construction progress

35.25% of construction complete · last inspected by DLD 16 Jul 2026

on pace — ≈17 pts behind the plan as of the last inspection

today
inspected 16 Jul 2026
start 1 Jul 2025 est. finish 1 Jul 2027