Active
Progress
50.08%
Handover
~ Sept 2026
Escrow
#100090174781

Oasis Loft

#3424 · OASIS LOFTS PROPERTIES L.L.C · Nadd Hessa · 164 units

declared value 62.4M AED data last checked 12 Sept 2026

B + G + 2P + 9 Typical Floors + Roof Floors.The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

50.08% of construction complete · last inspected by DLD 8 Jun 2026

≈34 pts behind the planned pace as of the last inspection

today
inspected 8 Jun 2026
start 1 Oct 2024 est. finish 30 Sept 2026