photo: mirfa.comUnder constructionNUMA RESERVE
DLD developer no. 2052 · MIRFA SERENITY REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
G+2+R (35 villas)
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 16 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 503.72 | 5,422 | 16,700,000 | 33,153 | 3,080 |
| 29 Jun 2026 | Sales | Off-plan | Villa · 5 B/R | 399.55 | 4,301 | 10,791,000 | 27,008 | 2,509 |
| 17 Jun 2026 | Sales | Off-plan | Villa · 5 B/R | 399.55 | 4,301 | 11,990,000 | 30,009 | 2,788 |
| 1 Jun 2026 | Sales | Off-plan | Villa · 5 B/R | 396.74 | 4,270 | 13,480,000 | 33,977 | 3,157 |
| 18 May 2026 | Sales | Off-plan | Villa · 5 B/R | 464.55 | 5,000 | 13,580,000 | 29,233 | 2,716 |
| 18 May 2026 | Sales | Off-plan | Villa · 5 B/R | 402.17 | 4,329 | 12,099,000 | 30,084 | 2,795 |
| 18 May 2026 | Sales | Off-plan | Villa · 5 B/R | 457.27 | 4,922 | 13,580,000 | 29,698 | 2,759 |
| 18 May 2026 | Sales | Off-plan | Villa · 5 B/R | 399.55 | 4,301 | 11,990,000 | 30,009 | 2,788 |
| 18 May 2026 | Sales | Off-plan | Villa · 5 B/R | 399.54 | 4,301 | 12,490,000 | 31,261 | 2,904 |
| 13 May 2026 | Sales | Off-plan | Villa · 5 B/R | 395.56 | 4,258 | 13,480,000 | 34,078 | 3,166 |
| 10 May 2026 | Sales | Off-plan | Villa · 5 B/R | 410.69 | 4,421 | 12,490,000 | 30,412 | 2,825 |
| 10 May 2026 | Sales | Off-plan | Villa · 5 B/R | 458.38 | 4,934 | 13,980,000 | 30,499 | 2,833 |
| 10 May 2026 | Sales | Off-plan | Villa · 5 B/R | 464.51 | 5,000 | 13,580,000 | 29,235 | 2,716 |
| 10 May 2026 | Sales | Off-plan | Villa · 5 B/R | 399.54 | 4,301 | 11,990,000 | 30,010 | 2,788 |
| 10 May 2026 | Sales | Off-plan | Villa · 5 B/R | 399.56 | 4,301 | 11,990,000 | 30,008 | 2,788 |
NUMA RESERVE: common questions
Is NUMA RESERVE delayed?
It is behind plan. Construction was 10.3% complete at the last DLD inspection on 5 October 2026, while its registered timeline (planned completion 31 December 2026) would expect about 85% by then.
When is the handover of NUMA RESERVE?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of NUMA RESERVE is built?
Construction was 10.3% complete at the last DLD inspection on 5 October 2026, as published by Dubai Land Department.
Where is NUMA RESERVE located?
NUMA RESERVE is in Wadi Al Safa 3, Dubai.
Who is the developer of NUMA RESERVE?
NUMA RESERVE is developed by MIRFA SERENITY REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2052). It is registered with Dubai Land Department as project no. 3786, with 35 units.
Does NUMA RESERVE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205900652703. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in NUMA RESERVE?
The most recent sale registered with Dubai Land Department was on 16 July 2026 for AED 16,700,000. Across the 26 recorded sales, the average was AED 2,908 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.