photo: alansariproperties.comDelayed 1 mo.Nova Tower
DLD developer no. 1294 · ALANSARI REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
B+G+2p+21+Roof
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 20 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 81.64 | 879 | 1,370,000 | 16,781 | 1,559 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 126.91 | 1,366 | 1,767,000 | 13,923 | 1,294 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 89.77 | 966 | 1,301,500 | 14,498 | 1,347 |
| 23 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 90.08 | 970 | 1,380,000 | 15,320 | 1,423 |
| 8 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 125.13 | 1,347 | 1,795,200 | 14,347 | 1,333 |
| 20 May 2026 | Sales | Off-plan | Flat · 2 B/R | 147.88 | 1,592 | 2,080,000 | 14,065 | 1,307 |
| 20 May 2026 | Sales | Off-plan | Flat · 1 B/R | 90.32 | 972 | 1,390,000 | 15,390 | 1,430 |
| 15 May 2026 | Sales | Off-plan | Flat · 2 B/R | 126.27 | 1,359 | 1,790,400 | 14,179 | 1,317 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 91.23 | 982 | 1,420,000 | 15,565 | 1,446 |
| 15 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 84.14 | 906 | 1,406,000 | 16,710 | 1,552 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 81.64 | 879 | 1,360,000 | 16,659 | 1,548 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 147.88 | 1,592 | 2,070,000 | 13,998 | 1,300 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 89.14 | 959 | 1,380,000 | 15,481 | 1,438 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 83.12 | 895 | 1,295,000 | 15,580 | 1,447 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 145.39 | 1,565 | 2,088,000 | 14,361 | 1,334 |
Nova Tower: common questions
Is Nova Tower delayed?
It is behind plan. Construction was 40.1% complete at the last DLD inspection on 3 August 2026, while its registered timeline (planned completion 26 September 2026) would expect about 92% by then.
When is the handover of Nova Tower?
The planned completion date registered with Dubai Land Department is 26 September 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Nova Tower is built?
Construction was 40.1% complete at the last DLD inspection on 3 August 2026, as published by Dubai Land Department.
Where is Nova Tower located?
Nova Tower is in Dubai Science Park, Dubai. Dubai Land Department records it under the Al Barshaa South Second area.
Who is the developer of Nova Tower?
Nova Tower is developed by ALANSARI REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1294). It is registered with Dubai Land Department as project no. 3870, with 134 units.
Does Nova Tower have an escrow account?
Yes. Dubai Land Department open data lists escrow account 10447871920013. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Nova Tower?
The most recent sale registered with Dubai Land Department was on 20 August 2026 for AED 1,370,000. Across the 53 recorded sales, the average was AED 1,395 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.