photo: nakheel.comUnder constructionDeveloper: District One - Fz
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Nakheel →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 72.92 | 785 | 1,470,000 | 20,159 | 1,873 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 74.43 | 801 | 1,686,800 | 22,663 | 2,105 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 133.57 | 1,438 | 3,422,800 | 25,626 | 2,381 |
| 28 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 80.76 | 869 | 1,735,800 | 21,493 | 1,997 |
| 14 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 73.82 | 795 | 1,349,878.31 | 18,286 | 1,699 |
| 6 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.98 | 786 | 1,560,800 | 21,387 | 1,987 |
| 15 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 73.49 | 791 | 1,578,880 | 21,484 | 1,996 |
| 10 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 74.43 | 801 | 1,600,000 | 21,497 | 1,997 |
| 8 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 73.49 | 791 | 1,563,800 | 21,279 | 1,977 |
| 4 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.12 | 798 | 1,836,800 | 24,781 | 2,302 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 189.02 | 2,035 | 4,521,800 | 23,922 | 2,222 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 113.89 | 1,226 | 2,640,800 | 23,187 | 2,154 |
| 14 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 204.96 | 2,206 | 5,445,800 | 26,570 | 2,468 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 73.31 | 789 | 1,567,800 | 21,386 | 1,987 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 201.7 | 2,171 | 3,964,800 | 19,657 | 1,826 |
Naya at District One: common questions
Is Naya at District One delayed?
Not by DLD figures. Construction was 56% complete at the last DLD inspection on 22 July 2026, in line with or ahead of its registered timeline (about 70% expected by then, planned completion 30 September 2027).
When is the handover of Naya at District One?
The planned completion date registered with Dubai Land Department is 30 September 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Naya at District One is built?
Construction was 56% complete at the last DLD inspection on 22 July 2026, as published by Dubai Land Department.
Where is Naya at District One located?
Naya at District One is in Al Merkadh, Dubai.
Who is the developer of Naya at District One?
Naya at District One is developed by District One - Fz. It is registered with Dubai Land Department as project no. 2674.
Does Naya at District One have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582334177801. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Naya at District One?
The most recent sale registered with Dubai Land Department was on 13 October 2026 for AED 1,470,000. Across the 17 recorded sales, the average was AED 2,179 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.