MR.C RESIDENCES DOWNTOWNphoto: altadevelopment.aeFinished
Progress
73.23%
Handover
~ Jan 2027
Escrow
#001640221011401

MR.C RESIDENCES DOWNTOWN

#2476 · Alta Real Estate Development L.L.C · Al Wasl

data last checked 17 Jul 2026

Construction progress

73.23% of construction complete · last inspected by DLD 4 Aug 2026

on pace — ≈18 pts behind the plan as of the last inspection

today
inspected 4 Aug 2026
start 11 Sept 2021 est. finish 27 Jan 2027
Google · this project