MOONSA Residencesphoto: dugasta.comActive
Progress
95.02%
Handover
Escrow
#019000081049

MOONSA Residences

#2834 · DUGASTA PROPERTIES DEVELOPMENT L.L.C · International City Ph 2 & 3

data last checked 17 Jul 2026

Construction progress

95.02% of construction complete · last inspected by DLD 31 Mar 2026

overdue — planned finish was 25 Aug 2025, still at 95.02%

today
inspected 31 Mar 2026
start 2 Jan 2024 est. finish 25 Aug 2025