Montivaphoto: emaar.comUnder construction

Montiva

DLD project no. 3744 · Al Khairan First

Progress
5.85%
DLD inspected 22 Apr 2026
Handover
~ Sept 2029
Est. finish 30 Sept 2029
Escrow
#3538453986209
Registered escrow account
Google rating
5.0 ★
3 reviews

DLD developer no. 1224 · DUBAI CREEK HARBOUR L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Emaar →
DLDConstruction inspection
5.85% of construction complete · last inspected by DLD 22 Apr 2026

on pace — ≈6 pts behind the plan as of the last inspection

today
inspected 22 Apr 2026
start 30 Oct 2025 est. finish 30 Sept 2029
Google · this project
5.0
3 reviews

Location

Montiva: common questions

Is Montiva delayed?

Not by DLD figures. Construction was 5.85% complete at the last DLD inspection on 22 April 2026, in line with or ahead of its registered timeline (about 12% expected by then, planned completion 30 September 2029).

When is the handover of Montiva?

The planned completion date registered with Dubai Land Department is 30 September 2029. Handover usually follows completion; the developer confirms the exact date.

How much of Montiva is built?

Construction was 5.85% complete at the last DLD inspection on 22 April 2026, as published by Dubai Land Department.

Where is Montiva located?

Montiva is in Al Khairan First, Dubai.

Who is the developer of Montiva?

Montiva is developed by DUBAI CREEK HARBOUR L.L.C (DLD developer no. 1224). It is registered with Dubai Land Department as project no. 3744.

Does Montiva have an escrow account?

Yes. Dubai Land Department open data lists escrow account 3538453986209. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Montiva?

The most recent sale registered with Dubai Land Department was on 21 August 2026 for AED 2,864,888. Across the 68 recorded sales, the average was AED 2,424 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.