photo: keymavensgroup.comUnder constructionMONTAGE
Developer: Key Mavens Montage Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 9 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 58.01 | 624 | 970,000 | 16,721 | 1,553 |
| 27 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 92.6 | 997 | 1,607,337 | 17,358 | 1,613 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 87.51 | 942 | 1,350,000 | 15,427 | 1,433 |
| 11 May 2026 | Sales | Off-plan | Flat · 1 B/R | 57.61 | 620 | 1,144,479 | 19,866 | 1,846 |
| 11 May 2026 | Sales | Off-plan | Flat · 1 B/R | 61.81 | 665 | 1,289,049 | 20,855 | 1,937 |
| 11 May 2026 | Sales | Off-plan | Flat · 1 B/R | 64.14 | 690 | 1,325,047 | 20,659 | 1,919 |
| 4 May 2026 | Sales | Off-plan | Flat · 2 B/R | 87.51 | 942 | 1,744,214 | 19,932 | 1,852 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 61.81 | 665 | 1,348,712 | 21,820 | 2,027 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 87.51 | 942 | 1,762,132 | 20,136 | 1,871 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 87.62 | 943 | 1,838,782 | 20,986 | 1,950 |
| 30 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 85.33 | 918 | 1,699,194 | 19,913 | 1,850 |
| 30 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 55.92 | 602 | 1,289,591 | 23,061 | 2,142 |
| 30 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 64.14 | 690 | 1,236,128 | 19,272 | 1,790 |
| 30 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 90.01 | 969 | 1,690,316 | 18,779 | 1,745 |
| 30 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 86.5 | 931 | 1,699,881 | 19,652 | 1,826 |
MONTAGE: common questions
Is MONTAGE delayed?
It is behind plan. Construction was 30.57% complete at the last DLD inspection on 6 August 2026, while its registered timeline (planned completion 31 August 2027) would expect about 64% by then.
When is the handover of MONTAGE?
The planned completion date registered with Dubai Land Department is 31 August 2027. Handover usually follows completion; the developer confirms the exact date.
How much of MONTAGE is built?
Construction was 30.57% complete at the last DLD inspection on 6 August 2026, as published by Dubai Land Department.
Where is MONTAGE located?
MONTAGE is in Jaddaf Waterfront, Dubai.
Who is the developer of MONTAGE?
MONTAGE is developed by Key Mavens Montage Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3212.
Does MONTAGE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 994000057378. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in MONTAGE?
The most recent sale registered with Dubai Land Department was on 9 October 2026 for AED 970,000. Across the 46 recorded sales, the average was AED 1,863 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.