MONTAGEphoto: keymavensgroup.comUnder construction

MONTAGE

DLD project no. 3212 · Jaddaf Waterfront

Progress
30.57%
DLD inspected 6 Aug 2026
Handover
~ Aug 2027
Est. finish 31 Aug 2027
Escrow
#994000057378
Registered escrow account
Google rating
5.0 ★
11 reviews

Developer: Key Mavens Montage Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
30.57% of construction complete · last inspected by DLD 6 Aug 2026

≈34 pts behind the planned pace as of the last inspection

today
inspected 6 Aug 2026
start 1 Sept 2024 est. finish 31 Aug 2027
Google · this project
5.0
11 reviews

Location

MONTAGE: common questions

Is MONTAGE delayed?

It is behind plan. Construction was 30.57% complete at the last DLD inspection on 6 August 2026, while its registered timeline (planned completion 31 August 2027) would expect about 64% by then.

When is the handover of MONTAGE?

The planned completion date registered with Dubai Land Department is 31 August 2027. Handover usually follows completion; the developer confirms the exact date.

How much of MONTAGE is built?

Construction was 30.57% complete at the last DLD inspection on 6 August 2026, as published by Dubai Land Department.

Where is MONTAGE located?

MONTAGE is in Jaddaf Waterfront, Dubai.

Who is the developer of MONTAGE?

MONTAGE is developed by Key Mavens Montage Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3212.

Does MONTAGE have an escrow account?

Yes. Dubai Land Department open data lists escrow account 994000057378. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in MONTAGE?

The most recent sale registered with Dubai Land Department was on 9 October 2026 for AED 970,000. Across the 46 recorded sales, the average was AED 1,863 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.