photo: karmadevelopers.aeUnder constructionMilos By Karma
DLD developer no. 1645 · KARMA REALTY DEVELOPERS L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 19 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 84.18 | 906 | 1,087,157.61 | 12,915 | 1,200 |
| 9 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 91.26 | 982 | 1,169,323 | 12,813 | 1,190 |
| 7 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 81.2 | 874 | 1,125,377 | 13,859 | 1,288 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 85.02 | 915 | 1,123,051 | 13,209 | 1,227 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 85.02 | 915 | 1,150,000 | 13,526 | 1,257 |
| 14 May 2026 | Sales | Off-plan | Flat · 1 B/R | 91.36 | 983 | 1,211,034.02 | 13,256 | 1,231 |
| 6 May 2026 | Sales | Off-plan | Flat · 1 B/R | 66.74 | 718 | 939,636 | 14,079 | 1,308 |
| 6 May 2026 | Sales | Off-plan | Flat · 1 B/R | 67.32 | 725 | 896,822 | 13,322 | 1,238 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 66.87 | 720 | 871,453 | 13,032 | 1,211 |
| 24 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 91.36 | 983 | 1,134,655 | 12,420 | 1,154 |
| 24 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 81.21 | 874 | 1,044,329 | 12,860 | 1,195 |
| 24 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 72.88 | 784 | 972,281 | 13,341 | 1,239 |
| 17 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 72.88 | 784 | 948,055 | 13,008 | 1,209 |
| 17 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 78.63 | 846 | 1,058,068.26 | 13,456 | 1,250 |
| 27 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 91.26 | 982 | 1,211,367 | 13,274 | 1,233 |
Milos By Karma: common questions
Is Milos By Karma delayed?
It is behind plan. Construction was 0.44% complete at the last DLD inspection on 22 April 2026, while its registered timeline (planned completion 1 April 2027) would expect about 65% by then.
When is the handover of Milos By Karma?
The planned completion date registered with Dubai Land Department is 1 April 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Milos By Karma is built?
Construction was 0.44% complete at the last DLD inspection on 22 April 2026, as published by Dubai Land Department.
Where is Milos By Karma located?
Milos By Karma is in Dubai Land Residence Complex, Dubai.
Who is the developer of Milos By Karma?
Milos By Karma is developed by KARMA REALTY DEVELOPERS L.L.C (DLD developer no. 1645). It is registered with Dubai Land Department as project no. 3132.
Does Milos By Karma have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1091225838233007. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Milos By Karma?
The most recent sale registered with Dubai Land Department was on 19 September 2026 for AED 1,087,158. Across the 16 recorded sales, the average was AED 1,226 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.