MERCER HOUSEphoto: ellingtonproperties.comUnder construction

MERCER HOUSE

DLD project no. 2990 · Al Thanyah Fifth

Progress
18.11%
DLD inspected 7 Aug 2026
Handover
~ Jul 2027
Est. finish 31 Jul 2027
Escrow
#12565423920005
Registered escrow account
Google rating
4.6 ★
5 reviews

Developer: Eln Properties Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Ellington →
DLDConstruction inspection
18.11% of construction complete · last inspected by DLD 7 Aug 2026

≈53 pts behind the planned pace as of the last inspection

today
inspected 7 Aug 2026
start 1 Mar 2024 est. finish 31 Jul 2027
Google · this project
4.6
5 reviews

Location

MERCER HOUSE: common questions

Is MERCER HOUSE delayed?

It is behind plan. Construction was 18.11% complete at the last DLD inspection on 7 August 2026, while its registered timeline (planned completion 31 July 2027) would expect about 71% by then.

When is the handover of MERCER HOUSE?

The planned completion date registered with Dubai Land Department is 31 July 2027. Handover usually follows completion; the developer confirms the exact date.

How much of MERCER HOUSE is built?

Construction was 18.11% complete at the last DLD inspection on 7 August 2026, as published by Dubai Land Department.

Where is MERCER HOUSE located?

MERCER HOUSE is in Al Thanyah Fifth, Dubai.

Who is the developer of MERCER HOUSE?

MERCER HOUSE is developed by Eln Properties Development L.L.C. It is registered with Dubai Land Department as project no. 2990.

Does MERCER HOUSE have an escrow account?

Yes. Dubai Land Department open data lists escrow account 12565423920005. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in MERCER HOUSE?

The most recent sale registered with Dubai Land Department was on 21 September 2026 for AED 1,328,828. Across the 43 recorded sales, the average was AED 2,675 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.