MERCER HOUSEphoto: ellingtonproperties.comActive
Progress
18.11%
Handover
~ Jul 2027
Escrow
#12565423920005

MERCER HOUSE

#2990 · Eln Properties Development L.L.C · Al Thanyah Fifth

More from Ellington
data last checked 17 Jul 2026

Construction progress

18.11% of construction complete · last inspected by DLD 7 Aug 2026

≈53 pts behind the planned pace as of the last inspection

today
inspected 7 Aug 2026
start 1 Mar 2024 est. finish 31 Jul 2027