photo: binghatti.comUnder constructionDLD developer no. 1051 · Binghatti Developers FZE
Data last checked 29 Oct 2026
More from Binghatti →3B+G+5P+HC+3 Amenities + 3 MECH +3 MECH (NON ACCESSIBLE) + 51 Residential Floors+3 Services +Roof
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 12 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 170.66 | 1,837 | 8,000,000 | 46,877 | 4,355 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 305.06 | 3,284 | 18,000,000 | 59,005 | 5,482 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 4 B/R | 375.57 | 4,043 | 36,299,999 | 96,653 | 8,979 |
| 5 Sept 2026 | Mortgage | Off-plan | Flat · 2 B/R | 235.5 | 2,535 | 3,680,000 | 15,626 | 1,452 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 3 B/R | 251.85 | 2,711 | 15,000,000 | 59,559 | 5,533 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 235.5 | 2,535 | 10,000,000 | 42,463 | 3,945 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 170.66 | 1,837 | 8,500,000 | 49,807 | 4,627 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 170.66 | 1,837 | 8,500,000 | 49,807 | 4,627 |
| 19 Aug 2026 | Sales | Off-plan | Flat · 3 B/R | 251.85 | 2,711 | 22,099,999 | 87,751 | 8,152 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 235.5 | 2,535 | 10,379,999.4 | 44,076 | 4,095 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 4 B/R | 331.49 | 3,568 | 30,000,000 | 90,500 | 8,408 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 4 B/R | 331.5 | 3,568 | 30,000,000 | 90,498 | 8,408 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 235.5 | 2,535 | 8,500,000 | 36,093 | 3,353 |
| 9 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 235.5 | 2,535 | 12,159,999 | 51,635 | 4,797 |
| 8 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 318.48 | 3,428 | 21,300,000 | 66,880 | 6,213 |
Mercedes-Benz Places | Binghatti: common questions
Is Mercedes-Benz Places | Binghatti delayed?
Not by DLD figures. Construction was 65.25% complete at the last DLD inspection on 28 April 2026, in line with or ahead of its registered timeline (about 78% expected by then, planned completion 31 December 2026).
When is the handover of Mercedes-Benz Places | Binghatti?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Mercedes-Benz Places | Binghatti is built?
Construction was 65.25% complete at the last DLD inspection on 28 April 2026, as published by Dubai Land Department.
Where is Mercedes-Benz Places | Binghatti located?
Mercedes-Benz Places | Binghatti is in Burj Khalifa, Dubai.
Who is the developer of Mercedes-Benz Places | Binghatti?
Mercedes-Benz Places | Binghatti is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 2545, with 163 units.
Does Mercedes-Benz Places | Binghatti have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0011370621096. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Mercedes-Benz Places | Binghatti?
The most recent sale registered with Dubai Land Department was on 12 October 2026 for AED 8,000,000. Across the 20 recorded sales, the average was AED 5,977 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.