photo: mbl-signature-jlt.aeUnder constructionMBL Signature
Developer: Mag 10 Property Development Dmcc
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Sales | Off-plan | Flat · Studio | 56.05 | 603 | 1,010,000 | 18,020 | 1,674 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 50.41 | 543 | 433,203.74 | 8,594 | 798 |
| 20 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 84.4 | 908 | 1,763,761.27 | 20,898 | 1,941 |
| 20 Aug 2026 | Sales | Off-plan | Flat · Studio | 57.18 | 615 | 1,590,000 | 27,807 | 2,583 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 154.86 | 1,667 | 2,372,753.73 | 15,322 | 1,423 |
| 12 Aug 2026 | Sales | Off-plan | Flat · Studio | 54.81 | 590 | 1,564,294.84 | 28,540 | 2,651 |
| 22 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 220.39 | 2,372 | 5,792,753 | 26,284 | 2,442 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 84.37 | 908 | 1,449,390 | 17,179 | 1,596 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 84.4 | 908 | 1,438,361.57 | 17,042 | 1,583 |
| 6 Jul 2026 | Sales | Off-plan | Flat · Studio | 56.05 | 603 | 476,268.14 | 8,497 | 789 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 202.47 | 2,179 | 4,395,202 | 21,708 | 2,017 |
| 23 Jun 2026 | Sales | Off-plan | Flat · Studio | 49.83 | 536 | 1,030,430 | 20,679 | 1,921 |
| 23 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 84.4 | 908 | 1,391,962.81 | 16,492 | 1,532 |
| 18 Jun 2026 | Sales | Off-plan | Flat · Studio | 50.41 | 543 | 433,203.68 | 8,594 | 798 |
| 18 Jun 2026 | Sales | Off-plan | Flat · Studio | 50.41 | 543 | 433,203.7 | 8,594 | 798 |
MBL Signature: common questions
Is MBL Signature delayed?
Not by DLD figures. Construction was 60.1% complete at the last DLD inspection on 6 May 2026, in line with or ahead of its registered timeline (about 53% expected by then, planned completion 31 March 2027).
When is the handover of MBL Signature?
The planned completion date registered with Dubai Land Department is 31 March 2027. Handover usually follows completion; the developer confirms the exact date.
How much of MBL Signature is built?
Construction was 60.1% complete at the last DLD inspection on 6 May 2026, as published by Dubai Land Department.
Where is MBL Signature located?
MBL Signature is in Jumeirah Lakes Towers (JLT), Dubai.
Who is the developer of MBL Signature?
MBL Signature is developed by Mag 10 Property Development Dmcc. It is registered with Dubai Land Department as project no. 3780.
Does MBL Signature have an escrow account?
Yes. Dubai Land Department open data lists escrow account 13999555920003. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in MBL Signature?
The most recent sale registered with Dubai Land Department was on 26 October 2026 for AED 1,010,000. Across the 49 recorded sales, the average was AED 2,005 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.