Mareva 2 The Oasisphoto: emaar.comActive
Progress
1.32%
Handover
~ Feb 2030
Escrow
#3538215410324

Mareva 2 The Oasis

#4270 · EMAAR DEVELOPMENT P.J.S.C. · Me'Aisem Second · 347 units

More from Emaar
declared value 1.1B AED data last checked 12 Sept 2026

Residential development consisting of 347 villas (B+G+2)

Construction progress

1.32% of construction complete · last inspected by DLD 6 Jul 2026

on pace — ≈6 pts behind the plan as of the last inspection

today
inspected 6 Jul 2026
start 22 Mar 2026 est. finish 28 Feb 2030
Google · this project
5.0
1 reviews