Active
Progress
37.75%
Handover
~ Sept 2026
Escrow
#3001748265000

Mangrove 2

#3597 · MANGROVE REAL ESTATE DEVELOPMENT L.L.C · Wadi Al Safa 3 · 18 units

declared value 8.4M AED data last checked 12 Sept 2026

B+G+4 Floors + Roof Commercial Offices and Retails

Construction progress

37.75% of construction complete · last inspected by DLD 10 Aug 2026

≈53 pts behind the planned pace as of the last inspection

today
inspected 10 Aug 2026
start 23 May 2025 est. finish 23 Sept 2026