photo: makdevelopers.comUnder constructionMAK I'Sola Bella
Developer: Mak Developers L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 67.57 | 727 | 964,656 | 14,276 | 1,326 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 67.35 | 725 | 1,262,250 | 18,742 | 1,741 |
| 20 Aug 2026 | Sales | Off-plan | Flat · Studio | 38.4 | 413 | 740,000 | 19,271 | 1,790 |
| 11 Jun 2026 | Sales | Off-plan | Flat · Studio | 38.4 | 413 | 705,000 | 18,359 | 1,706 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 38.24 | 412 | 750,000 | 19,613 | 1,822 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 38.4 | 413 | 750,000 | 19,531 | 1,815 |
| 29 Apr 2026 | Sales | Off-plan | Flat · Studio | 38.4 | 413 | 752,000 | 19,583 | 1,819 |
| 17 Apr 2026 | Sales | Off-plan | Flat · Studio | 38.4 | 413 | 720,000 | 18,750 | 1,742 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 68.63 | 739 | 1,225,000 | 17,849 | 1,658 |
| 18 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 81.63 | 879 | 1,375,000 | 16,844 | 1,565 |
| 17 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 69.46 | 748 | 1,275,000 | 18,356 | 1,705 |
| 17 Mar 2026 | Sales | Off-plan | Flat · Studio | 38.24 | 412 | 800,000 | 20,921 | 1,944 |
| 3 Feb 2026 | Sales | Off-plan | Flat · Studio | 38.31 | 412 | 755,000 | 19,708 | 1,831 |
| 29 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 68.63 | 739 | 1,050,000 | 15,299 | 1,421 |
| 27 Jan 2026 | Sales | Off-plan | Flat · Studio | 38.24 | 412 | 736,250 | 19,253 | 1,789 |
MAK I'Sola Bella: common questions
Is MAK I'Sola Bella delayed?
It is behind plan. Construction was 27.17% complete at the last DLD inspection on 20 August 2026, while its registered timeline (planned completion 5 September 2027) would expect about 65% by then.
When is the handover of MAK I'Sola Bella?
The planned completion date registered with Dubai Land Department is 5 September 2027. Handover usually follows completion; the developer confirms the exact date.
How much of MAK I'Sola Bella is built?
Construction was 27.17% complete at the last DLD inspection on 20 August 2026, as published by Dubai Land Department.
Where is MAK I'Sola Bella located?
MAK I'Sola Bella is in Jumeirah Village Circle (JVC), Dubai.
Who is the developer of MAK I'Sola Bella?
MAK I'Sola Bella is developed by Mak Developers L.L.C. It is registered with Dubai Land Department as project no. 3096.
Does MAK I'Sola Bella have an escrow account?
Yes. Dubai Land Department open data lists escrow account 13409993920002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in MAK I'Sola Bella?
The most recent sale registered with Dubai Land Department was on 5 October 2026 for AED 964,656. Across the 18 recorded sales, the average was AED 1,726 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.