MAISON MARGIELA RESIDENCESphoto: altadevelopment.aeActive
Progress
5.87%
Handover
~ Mar 2028
Escrow
#4031226965244003

MAISON MARGIELA RESIDENCES

#3716 · Alta Real Estate Development L.L.C ·

data last checked 17 Jul 2026

Construction progress

5.87% of construction complete · last inspected by DLD 2 Jul 2026

≈36 pts behind the planned pace as of the last inspection

today
inspected 2 Jul 2026
start 28 Mar 2025 est. finish 27 Mar 2028