MAISON MARGIELA RESIDENCESphoto: altadevelopment.aeUnder construction

MAISON MARGIELA RESIDENCES

DLD project no. 3716 · —

Progress
6.38%
DLD inspected 5 Oct 2026
Handover
~ Mar 2028
Est. finish 27 Mar 2028
Escrow
#4031226965244003
Registered escrow account
Google rating
4.8 ★
12 reviews

Developer: Alta Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
6.38% of construction complete · last inspected by DLD 5 Oct 2026

≈44 pts behind the planned pace as of the last inspection

today
inspected 5 Oct 2026
start 28 Mar 2025 est. finish 27 Mar 2028
Google · this project
4.8
12 reviews

Location

MAISON MARGIELA RESIDENCES: common questions

Is MAISON MARGIELA RESIDENCES delayed?

It is behind plan. Construction was 6.38% complete at the last DLD inspection on 5 October 2026, while its registered timeline (planned completion 27 March 2028) would expect about 51% by then.

When is the handover of MAISON MARGIELA RESIDENCES?

The planned completion date registered with Dubai Land Department is 27 March 2028. Handover usually follows completion; the developer confirms the exact date.

How much of MAISON MARGIELA RESIDENCES is built?

Construction was 6.38% complete at the last DLD inspection on 5 October 2026, as published by Dubai Land Department.

Who is the developer of MAISON MARGIELA RESIDENCES?

MAISON MARGIELA RESIDENCES is developed by Alta Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3716.

Does MAISON MARGIELA RESIDENCES have an escrow account?

Yes. Dubai Land Department open data lists escrow account 4031226965244003. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.