photo: pantheondevelopment.aeUnder constructionMAISON ELYSEE III BY PANTHEON
DLD developer no. 1364 · PANTHEON ELYSEE REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 57.69 | 621 | 599,900 | 10,399 | 966 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 58.4 | 629 | 670,000 | 11,473 | 1,066 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 58.29 | 627 | 584,900 | 10,034 | 932 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 57.69 | 621 | 1,079,900 | 18,719 | 1,739 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 58.29 | 627 | 721,905 | 12,385 | 1,151 |
| 9 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 58.81 | 633 | 1,064,900 | 18,107 | 1,682 |
| 18 Jun 2026 | Sales | Off-plan | Flat · Studio | 35.14 | 378 | 734,900 | 20,913 | 1,943 |
| 2 Jun 2026 | Sales | Off-plan | Flat · Studio | 36.69 | 395 | 759,900 | 20,711 | 1,924 |
| 22 May 2026 | Sales | Off-plan | Flat · Studio | 37.08 | 399 | 702,900 | 18,956 | 1,761 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 58.55 | 630 | 769,900 | 13,149 | 1,222 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 58.74 | 632 | 1,109,900 | 18,895 | 1,755 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 58.47 | 629 | 1,063,202 | 18,184 | 1,689 |
| 21 Apr 2026 | Sales | Off-plan | Flat · Studio | 36.69 | 395 | 719,900 | 19,621 | 1,823 |
| 20 Apr 2026 | Sales | Off-plan | Flat · Studio | 35.14 | 378 | 689,900 | 19,633 | 1,824 |
| 20 Apr 2026 | Sales | Off-plan | Flat · Studio | 36.69 | 395 | 709,900 | 19,349 | 1,798 |
MAISON ELYSEE III BY PANTHEON: common questions
Is MAISON ELYSEE III BY PANTHEON delayed?
It is behind plan. Construction was 4.39% complete at the last DLD inspection on 25 June 2026, while its registered timeline (planned completion 31 October 2027) would expect about 55% by then.
When is the handover of MAISON ELYSEE III BY PANTHEON?
The planned completion date registered with Dubai Land Department is 31 October 2027. Handover usually follows completion; the developer confirms the exact date.
How much of MAISON ELYSEE III BY PANTHEON is built?
Construction was 4.39% complete at the last DLD inspection on 25 June 2026, as published by Dubai Land Department.
Where is MAISON ELYSEE III BY PANTHEON located?
MAISON ELYSEE III BY PANTHEON is in Jumeirah Village Circle (JVC), Dubai.
Who is the developer of MAISON ELYSEE III BY PANTHEON?
MAISON ELYSEE III BY PANTHEON is developed by PANTHEON ELYSEE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1364). It is registered with Dubai Land Department as project no. 3281.
Does MAISON ELYSEE III BY PANTHEON have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1009765148. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in MAISON ELYSEE III BY PANTHEON?
The most recent sale registered with Dubai Land Department was on 13 October 2026 for AED 599,900. Across the 58 recorded sales, the average was AED 1,514 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.