photo: pantheondevelopment.aeUnder constructionMaison Elysee I
DLD developer no. 1364 · PANTHEON ELYSEE REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 7 Oct 2026 | Sales | Off-plan | Flat · Studio | 36.95 | 398 | 666,302 | 18,033 | 1,675 |
| 4 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 60.2 | 648 | 724,900 | 12,042 | 1,119 |
| 13 Aug 2026 | Gifts | Off-plan | Flat · 1 B/R | 60.37 | 650 | 950,004.35 | 15,736 | 1,462 |
| 6 Aug 2026 | Sales | Off-plan | Flat · Studio | 37.14 | 400 | 799,900 | 21,537 | 2,001 |
| 9 Jul 2026 | Sales | Off-plan | Flat · Studio | 35.37 | 381 | 653,301 | 18,470 | 1,716 |
| 8 Jul 2026 | Sales | Off-plan | Shop · NA | 61.1 | 658 | 1,996,534.32 | 32,677 | 3,036 |
| 9 Jun 2026 | Sales | Off-plan | Flat · Studio | 38.18 | 411 | 699,900 | 18,332 | 1,703 |
| 20 May 2026 | Sales | Off-plan | Flat · 1 B/R | 60.37 | 650 | 872,903 | 14,459 | 1,343 |
| 19 May 2026 | Sales | Off-plan | Flat · 1 B/R | 60.37 | 650 | 549,900 | 9,109 | 846 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 37.84 | 407 | 767,151 | 20,274 | 1,883 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 37.03 | 399 | 767,151 | 20,717 | 1,925 |
| 23 Apr 2026 | Sales | Off-plan | Shop · NA | 64.21 | 691 | 2,287,771 | 35,630 | 3,310 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 83.47 | 898 | 1,138,401 | 13,638 | 1,267 |
| 16 Apr 2026 | Sales | Off-plan | Flat · Studio | 37.14 | 400 | 669,900 | 18,037 | 1,676 |
| 3 Mar 2026 | Sales | Off-plan | Flat · Studio | 37.06 | 399 | 673,101 | 18,162 | 1,687 |
Maison Elysee I: common questions
Is Maison Elysee I delayed?
It is behind plan. Construction was 21.12% complete at the last DLD inspection on 6 July 2026, while its registered timeline (planned completion 31 March 2027) would expect about 76% by then.
When is the handover of Maison Elysee I?
The planned completion date registered with Dubai Land Department is 31 March 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Maison Elysee I is built?
Construction was 21.12% complete at the last DLD inspection on 6 July 2026, as published by Dubai Land Department.
Where is Maison Elysee I located?
Maison Elysee I is in Jumeirah Village Circle (JVC), Dubai.
Who is the developer of Maison Elysee I?
Maison Elysee I is developed by PANTHEON ELYSEE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1364). It is registered with Dubai Land Department as project no. 2905.
Does Maison Elysee I have an escrow account?
Yes. Dubai Land Department open data lists escrow account 12107757920010. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Maison Elysee I?
The most recent sale registered with Dubai Land Department was on 7 October 2026 for AED 666,302. Across the 39 recorded sales, the average was AED 1,580 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.