LUMO
DLD developer no. 1897 · WOG CAPITAL REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Residential Building (G+P+6)
This project on Google
Sale register covers the last ~3 months.
No sales match this filter in the stored window.
LUMO: common questions
Is LUMO delayed?
It is behind plan. Construction was 23.18% complete at the last DLD inspection on 1 September 2026, while its registered timeline (planned completion 22 February 2027) would expect about 68% by then.
When is the handover of LUMO?
The planned completion date registered with Dubai Land Department is 22 February 2027. Handover usually follows completion; the developer confirms the exact date.
How much of LUMO is built?
Construction was 23.18% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.
Where is LUMO located?
LUMO is in Palm Deira, Dubai.
Who is the developer of LUMO?
LUMO is developed by WOG CAPITAL REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1897). It is registered with Dubai Land Department as project no. 4527, with 54 units.
Does LUMO have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1001226975782002. Always confirm the account with the developer or in the Dubai REST app before paying.
Answers are generated from Dubai Land Department open data shown on this page.