Under construction

LUMO

DLD project no. 4527 · Palm Deira · 54 units

Progress
23.18%
DLD inspected 1 Sept 2026
Handover
~ Feb 2027
Est. finish 22 Feb 2027
Escrow
#1001226975782002
Registered escrow account
Google rating
—

DLD developer no. 1897 · WOG CAPITAL REAL ESTATE DEVELOPMENT L.L.C

Data last checked 29 Oct 2026

declared value 43.9M AED

Residential Building (G+P+6)

DLDConstruction inspection
23.18% of construction complete · last inspected by DLD 1 Sept 2026

≈45 pts behind the planned pace as of the last inspection

today
inspected 1 Sept 2026
start 23 Aug 2025 est. finish 22 Feb 2027
Google · this project
0 reviews

LUMO: common questions

Is LUMO delayed?

It is behind plan. Construction was 23.18% complete at the last DLD inspection on 1 September 2026, while its registered timeline (planned completion 22 February 2027) would expect about 68% by then.

When is the handover of LUMO?

The planned completion date registered with Dubai Land Department is 22 February 2027. Handover usually follows completion; the developer confirms the exact date.

How much of LUMO is built?

Construction was 23.18% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.

Where is LUMO located?

LUMO is in Palm Deira, Dubai.

Who is the developer of LUMO?

LUMO is developed by WOG CAPITAL REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1897). It is registered with Dubai Land Department as project no. 4527, with 54 units.

Does LUMO have an escrow account?

Yes. Dubai Land Department open data lists escrow account 1001226975782002. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.