photo: object-1.comDelayedDLD developer no. 1894 · OBJ1 REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
More from Object 1 →UG Watertank+G+5P+20+R Residential Building with Retail at Ground Floor.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 53.6 | 577 | 884,162 | 16,496 | 1,532 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 66.14 | 712 | 1,083,859 | 16,387 | 1,522 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 92.44 | 995 | 1,491,992 | 16,140 | 1,499 |
| 8 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 92.44 | 995 | 1,389,110 | 15,027 | 1,396 |
| 13 May 2026 | Sales | Off-plan | Flat · 1 B/R | 92.44 | 995 | 1,466,457 | 15,864 | 1,474 |
| 28 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 92.44 | 995 | 1,044,089 | 11,295 | 1,049 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 70.31 | 757 | 1,114,159.44 | 15,846 | 1,472 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 70.31 | 757 | 1,114,159.44 | 15,846 | 1,472 |
| 5 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 53.38 | 575 | 1,028,418 | 19,266 | 1,790 |
| 18 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 70.31 | 757 | 936,659 | 13,322 | 1,238 |
| 18 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 53.38 | 575 | 821,730 | 15,394 | 1,430 |
| 18 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 53.73 | 578 | 827,860 | 15,408 | 1,431 |
| 11 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 53.57 | 577 | 822,029 | 15,345 | 1,426 |
| 29 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 53.57 | 577 | 927,847 | 17,320 | 1,609 |
| 20 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 53.38 | 575 | 865,000 | 16,205 | 1,505 |
Luminar Tower 1: common questions
Is Luminar Tower 1 delayed?
It is behind plan. Construction was 33.07% complete at the last DLD inspection on 30 July 2026, while its registered timeline (planned completion 15 October 2026) would expect about 90% by then.
When is the handover of Luminar Tower 1?
The planned completion date registered with Dubai Land Department is 15 October 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Luminar Tower 1 is built?
Construction was 33.07% complete at the last DLD inspection on 30 July 2026, as published by Dubai Land Department.
Where is Luminar Tower 1 located?
Luminar Tower 1 is in Jumeirah Village Triangle (JVT), Dubai. Dubai Land Department records it under the Al Barsha South Fifth area.
Who is the developer of Luminar Tower 1?
Luminar Tower 1 is developed by OBJ1 REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1894). It is registered with Dubai Land Department as project no. 3183, with 200 units.
Does Luminar Tower 1 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 19304584. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Luminar Tower 1?
The most recent sale registered with Dubai Land Department was on 8 September 2026 for AED 884,162. Across the 18 recorded sales, the average was AED 1,388 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.