Active
Progress
11.42%
Handover
~ Apr 2028
Escrow
#0205894854004

Lumina

#3275 · Yehiaco Real Estate L.L.C · Dubai Healthcare City - Phase 1

data last checked 17 Jul 2026

Construction progress

11.42% of construction complete · last inspected by DLD 22 Jul 2026

≈41 pts behind the planned pace as of the last inspection

today
inspected 22 Jul 2026
start 1 Sept 2024 est. finish 1 Apr 2028