Lume Residencesphoto: lumeresidences.comActive
Progress
10.6%
Handover
~ Sept 2027
Escrow
unavailable

Lume Residences

#3550 · Jumeirah Village Circle

registry detail unavailable — outside current DLD window

No further description published for this project.

Construction progress

10.6% of construction complete · last inspected by DLD 1 Apr 2026

on pace — ≈23 pts behind the plan as of the last inspection

today
inspected 1 Apr 2026
start 30 Jun 2025 est. finish 30 Sept 2027