Lume Residencesphoto: lumeresidences.comUnder construction

Lume Residences

DLD project no. 3550 · Jumeirah Village Circle (JVC)

Progress
21.69%
DLD inspected 19 Aug 2026
Handover
~ Sept 2027
Est. finish 30 Sept 2027
Escrow
unavailable
No escrow account on file
Google rating
3.7 ★
3 reviews

DLD developer no. 1615 · S AND S REAL ESTATE DEVELOPMENT L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

registry detail unavailable — outside current DLD window
DLDConstruction inspection
21.69% of construction complete · last inspected by DLD 19 Aug 2026

≈29 pts behind the planned pace as of the last inspection

today
inspected 19 Aug 2026
start 30 Jun 2025 est. finish 30 Sept 2027
Google · this project
3.7
3 reviews

Location

Lume Residences: common questions

Is Lume Residences delayed?

It is behind plan. Construction was 21.69% complete at the last DLD inspection on 19 August 2026, while its registered timeline (planned completion 30 September 2027) would expect about 50% by then.

When is the handover of Lume Residences?

The planned completion date registered with Dubai Land Department is 30 September 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Lume Residences is built?

Construction was 21.69% complete at the last DLD inspection on 19 August 2026, as published by Dubai Land Department.

Where is Lume Residences located?

Lume Residences is in Jumeirah Village Circle (JVC), Dubai.

Who is the developer of Lume Residences?

Lume Residences is developed by S AND S REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1615). It is registered with Dubai Land Department as project no. 3550.

What are recent sale prices in Lume Residences?

The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 720,746. Across the 44 recorded sales, the average was AED 1,650 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.