Longfor International Center
DLD developer no. 2576 · STAR LANG REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Proposed (G+2P+6+R) Offices Building
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Sept 2026 | Sales | Off-plan | Office · NA | 117.26 | 1,262 | 1,591,888 | 13,576 | 1,261 |
| 25 Sept 2026 | Sales | Off-plan | Office · NA | 135.96 | 1,463 | 1,702,188 | 12,520 | 1,163 |
| 24 Sept 2026 | Sales | Off-plan | Office · NA | 187.67 | 2,020 | 2,314,888 | 12,335 | 1,146 |
| 24 Sept 2026 | Sales | Off-plan | Office · NA | 89.94 | 968 | 1,500,000 | 16,678 | 1,549 |
| 5 Sept 2026 | Sales | Off-plan | Office · NA | 116.7 | 1,256 | 1,761,658 | 15,096 | 1,402 |
| 18 Jul 2026 | Sales | Off-plan | Office · NA | 80.4 | 865 | 1,486,888 | 18,494 | 1,718 |
| 18 Jul 2026 | Sales | Off-plan | Office · NA | 133.33 | 1,435 | 2,125,888 | 15,945 | 1,481 |
| 2 Jul 2026 | Sales | Off-plan | Office · NA | 82.24 | 885 | 1,369,888 | 16,657 | 1,548 |
| 23 Jun 2026 | Sales | Off-plan | Office · NA | 82.24 | 885 | 1,306,143.6 | 15,882 | 1,475 |
| 22 Jun 2026 | Sales | Off-plan | Office · NA | 133.42 | 1,436 | 1,939,616.96 | 14,538 | 1,351 |
| 22 Jun 2026 | Sales | Off-plan | Office · NA | 116.7 | 1,256 | 1,755,616.96 | 15,044 | 1,398 |
| 22 Jun 2026 | Sales | Off-plan | Office · NA | 82.24 | 885 | 1,363,143.6 | 16,575 | 1,540 |
| 6 Jun 2026 | Sales | Off-plan | Office · NA | 89.94 | 968 | 1,515,888 | 16,854 | 1,566 |
| 6 Jun 2026 | Sales | Off-plan | Office · NA | 116.7 | 1,256 | 1,586,037 | 13,591 | 1,263 |
| 6 Jun 2026 | Sales | Off-plan | Office · NA | 85.13 | 916 | 1,209,217 | 14,204 | 1,320 |
Longfor International Center: common questions
Is Longfor International Center delayed?
It is behind plan. Construction was 1.64% complete at the last DLD inspection on 15 October 2026, while its registered timeline (planned completion 30 December 2027) would expect about 27% by then.
When is the handover of Longfor International Center?
The planned completion date registered with Dubai Land Department is 30 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Longfor International Center is built?
Construction was 1.64% complete at the last DLD inspection on 15 October 2026, as published by Dubai Land Department.
Where is Longfor International Center located?
Longfor International Center is in Warsan First, Dubai. Dubai Land Department records it under the Al Warsan First area.
Who is the developer of Longfor International Center?
Longfor International Center is developed by STAR LANG REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2576). It is registered with Dubai Land Department as project no. 4439, with 72 units.
Does Longfor International Center have an escrow account?
Yes. Dubai Land Department open data lists escrow account 200951434. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Longfor International Center?
The most recent sale registered with Dubai Land Department was on 28 September 2026 for AED 1,591,888. Across the 24 recorded sales, the average was AED 1,447 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.