photo: barcodevelopers.aeUnder constructionLivia Residence
Developer: Barco Properties Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.7 | 826 | 1,042,133 | 13,587 | 1,262 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 999,999 | 13,041 | 1,212 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 113.03 | 1,217 | 1,514,543 | 13,399 | 1,245 |
| 28 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 1,000,000 | 13,041 | 1,212 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 1,033,555 | 13,479 | 1,252 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 1,000,000 | 13,041 | 1,212 |
| 10 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 115.83 | 1,247 | 1,564,373 | 13,506 | 1,255 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 114.35 | 1,231 | 1,668,555 | 14,592 | 1,356 |
| 15 May 2026 | Sales | Off-plan | Flat · 2 B/R | 114.3 | 1,230 | 1,525,555 | 13,347 | 1,240 |
| 13 May 2026 | Sales | Off-plan | Flat · 2 B/R | 123.73 | 1,332 | 1,552,555 | 12,548 | 1,166 |
| 13 May 2026 | Sales | Off-plan | Flat · 1 B/R | 76.7 | 826 | 988,555 | 12,889 | 1,197 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.7 | 826 | 1,111,555 | 14,492 | 1,346 |
| 16 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 1,033,555 | 13,479 | 1,252 |
| 16 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.7 | 826 | 1,091,555 | 14,231 | 1,322 |
| 15 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 76.68 | 825 | 983,555 | 12,827 | 1,192 |
Livia Residence: common questions
Is Livia Residence delayed?
It is behind plan. Construction was 14.66% complete at the last DLD inspection on 30 July 2026, while its registered timeline (planned completion 30 April 2027) would expect about 59% by then.
When is the handover of Livia Residence?
The planned completion date registered with Dubai Land Department is 30 April 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Livia Residence is built?
Construction was 14.66% complete at the last DLD inspection on 30 July 2026, as published by Dubai Land Department.
Where is Livia Residence located?
Livia Residence is in Dubai South, Dubai.
Who is the developer of Livia Residence?
Livia Residence is developed by Barco Properties Development L.L.C. It is registered with Dubai Land Department as project no. 3687.
Does Livia Residence have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3718497555502. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Livia Residence?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 1,042,133. Across the 35 recorded sales, the average was AED 1,260 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.