LIV MARITIMEphoto: livuae.comActive
Progress
18.73%
Handover
~ Dec 2028
Escrow
#1009787712

LIV MARITIME

#3391 · L I V Maritime Real Estate Development L.L.C · Dubai Maritime City

data last checked 17 Jul 2026

Construction progress

18.73% of construction complete · last inspected by DLD 19 May 2026

on pace — ≈18 pts behind the plan as of the last inspection

today
inspected 19 May 2026
start 5 Nov 2024 est. finish 30 Dec 2028