photo: avenewdevelopment.aeUnder constructionLIA
DLD developer no. 1511 · AVENEW REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Mix use residential building G+P+8 Retail @ ground floor & gym, swimming pool @ 1st floor. Total Residential Units = 80 Units (1BHK=36 Units, 2BHK=36 Units, 3BHK=6 Units, Penthouse Simplex 2BHK=1 Units, Penthouse Simplex 5BHK=1 Units) and Retail Unit = 1 Unit
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 8 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 200.45 | 2,158 | 7,147,000 | 35,655 | 3,312 |
| 10 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 437.36 | 4,708 | 12,000,000 | 27,437 | 2,549 |
| 14 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 125.96 | 1,356 | 3,532,000 | 28,041 | 2,605 |
| 17 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 77.17 | 831 | 2,168,000 | 28,094 | 2,610 |
| 2 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 77.74 | 837 | 2,183,000 | 28,081 | 2,609 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 126.85 | 1,365 | 3,988,600 | 31,443 | 2,921 |
| 1 May 2026 | Sales | Off-plan | Flat · 2 B/R | 124.63 | 1,342 | 4,410,000 | 35,385 | 3,287 |
| 29 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 130.16 | 1,401 | 4,700,080 | 36,110 | 3,355 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 79.58 | 857 | 2,186,380 | 27,474 | 2,552 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 77.17 | 831 | 2,242,000 | 29,053 | 2,699 |
| 1 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 122.37 | 1,317 | 4,412,000 | 36,055 | 3,350 |
| 12 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 77.17 | 831 | 2,178,000 | 28,223 | 2,622 |
| 12 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 80.54 | 867 | 2,376,000 | 29,501 | 2,741 |
| 11 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 135.28 | 1,456 | 5,118,000 | 37,833 | 3,515 |
| 11 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 78.92 | 849 | 2,333,000 | 29,562 | 2,746 |
LIA: common questions
Is LIA delayed?
Not by DLD figures. Construction was 4.06% complete at the last DLD inspection on 2 October 2026, in line with or ahead of its registered timeline (about 25% expected by then, planned completion 20 May 2028).
When is the handover of LIA?
The planned completion date registered with Dubai Land Department is 20 May 2028. Handover usually follows completion; the developer confirms the exact date.
How much of LIA is built?
Construction was 4.06% complete at the last DLD inspection on 2 October 2026, as published by Dubai Land Department.
Where is LIA located?
LIA is in Palm Deira, Dubai.
Who is the developer of LIA?
LIA is developed by AVENEW REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1511). It is registered with Dubai Land Department as project no. 4195, with 82 units.
Does LIA have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582223588301. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in LIA?
The most recent sale registered with Dubai Land Department was on 8 September 2026 for AED 7,147,000. Across the 54 recorded sales, the average was AED 2,905 per sq ft.