Lexingtonphoto: nshama.aeActive
Progress
4.53%
Handover
~ Sept 2027
Escrow
#4031224702173074

Lexington

#3364 · NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C · Al Yelayiss 2

More from nshama
data last checked 17 Jul 2026

Construction progress

4.53% of construction complete · last inspected by DLD 13 Aug 2026

≈48 pts behind the planned pace as of the last inspection

today
inspected 13 Aug 2026
start 5 May 2025 est. finish 30 Sept 2027
Google · this project
0 reviews