LANAI Islandphoto: tilalalghaf.comActive
Progress
60.56%
Handover
~ Sept 2026
Escrow
#0205428840913

LANAI Island

#2498 · MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C · Al Hebiah Fourth · 27 units

declared value 832.9M AED data last checked 12 Sept 2026

27 Villas (B+G+1+R), (Old: - 13 Villas (B+G+1+R) Villas, The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

60.56% of construction complete · last inspected by DLD 9 Sept 2026

≈38 pts behind the planned pace as of the last inspection

today
inspected 9 Sept 2026
start 30 Apr 2023 est. finish 30 Sept 2026