Lacinaphoto: majidalfuttaimproperties.comActive
Progress
20.81%
Handover
~ Dec 2027
Escrow
#0205872406707

Lacina

#3336 · Majid Al Futtaim Ghaf Woods L.L.C · Wadi Al Safa 4

data last checked 17 Jul 2026

Construction progress

20.81% of construction complete · last inspected by DLD 6 Jul 2026

≈31 pts behind the planned pace as of the last inspection

today
inspected 6 Jul 2026
start 1 Dec 2024 est. finish 30 Dec 2027