photo: leosdevelopments.comUnder constructionKnightsbridge Park
Developer: Leos Sof Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 12 Oct 2026 | Sales | Off-plan | Villa · 5 B/R | 440.81 | 4,745 | 10,273,454.4 | 23,306 | 2,165 |
| 12 Oct 2026 | Sales | Off-plan | Villa · 6 B/R | 812.35 | 8,744 | 16,584,126.3 | 20,415 | 1,897 |
| 14 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 309.6 | 3,333 | 8,274,724 | 26,727 | 2,483 |
| 11 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 486.4 | 5,236 | 11,699,064.96 | 24,052 | 2,235 |
| 13 Aug 2026 | Sales | Off-plan | Villa · 4 B/R | 172.8 | 1,860 | 7,624,362 | 44,122 | 4,099 |
| 23 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 330.57 | 3,558 | 6,700,000 | 20,268 | 1,883 |
| 21 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 245.01 | 2,637 | 6,800,000 | 27,754 | 2,578 |
| 19 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 244.8 | 2,635 | 8,274,724 | 33,802 | 3,140 |
| 9 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 244.8 | 2,635 | 7,853,472 | 32,081 | 2,980 |
| 30 Jun 2026 | Sales | Off-plan | Villa · 4 B/R | 172.8 | 1,860 | 7,942,044 | 45,961 | 4,270 |
| 11 Jun 2026 | Sales | Off-plan | Villa · 4 B/R | 250.28 | 2,694 | 6,700,000 | 26,770 | 2,487 |
| 9 Jun 2026 | Sales | Off-plan | Villa · 4 B/R | 172.8 | 1,860 | 7,000,000 | 40,509 | 3,763 |
| 20 May 2026 | Sales | Off-plan | Villa · 4 B/R | 244.8 | 2,635 | 7,943,735 | 32,450 | 3,015 |
| 7 May 2026 | Sales | Off-plan | Villa · 4 B/R | 251.56 | 2,708 | 8,440,218 | 33,552 | 3,117 |
| 23 Apr 2026 | Sales | Off-plan | Villa · 4 B/R | 173.05 | 1,863 | 7,898,363 | 45,642 | 4,240 |
Knightsbridge Park: common questions
Is Knightsbridge Park delayed?
It is behind plan. Construction was 10.8% complete at the last DLD inspection on 5 August 2026, while its registered timeline (planned completion 15 November 2027) would expect about 51% by then.
When is the handover of Knightsbridge Park?
The planned completion date registered with Dubai Land Department is 15 November 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Knightsbridge Park is built?
Construction was 10.8% complete at the last DLD inspection on 5 August 2026, as published by Dubai Land Department.
Where is Knightsbridge Park located?
Knightsbridge Park is in Wadi Al Safa 3, Dubai.
Who is the developer of Knightsbridge Park?
Knightsbridge Park is developed by Leos Sof Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3361.
Does Knightsbridge Park have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205899233303. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Knightsbridge Park?
The most recent sale registered with Dubai Land Department was on 12 October 2026 for AED 10,273,454. Across the 25 recorded sales, the average was AED 3,178 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.