Jebel Ali Village Townhouses - Phase 3

#2387 · JEBEL ALI VILLAGE (L.L.C) · Jabal Ali First · 198 units

escrow #019000074208 declared value 274.7M AED

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

196 Villas with amenities.The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

100% of construction complete · last inspected by DLD 23 Apr 2026
inspected 23 Apr 2026
start 29 Sept 2022 est. finish 31 Dec 2025