Iridian Park 2photo: jre.aeActive
Progress
21.29%
Handover
~ Feb 2027
Escrow
#29539644

Iridian Park 2

#3765 · OBJ1 REAL ESTATE DEVELOPMENT L.L.C · Al Barsha South Fourth · 86 units

More from Object 1
declared value 26.0M AED data last checked 12 Sept 2026

U.G. W. Tank+ G + P + 5 + R Residential building

Construction progress

21.29% of construction complete · last inspected by DLD 31 Jul 2026

≈45 pts behind the planned pace as of the last inspection

today
inspected 31 Jul 2026
start 4 Aug 2025 est. finish 1 Feb 2027