photo: mered.aeUnder constructionICONIC
Developer: Mered Residences Real Estate L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 30 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 221.23 | 2,381 | 7,592,381.74 | 34,319 | 3,188 |
| 29 Sept 2026 | Gifts | Off-plan | Flat · 4 B/R | 251.22 | 2,704 | 10,550,004.04 | 41,995 | 3,901 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 80.7 | 869 | 3,895,111 | 48,267 | 4,484 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 148.56 | 1,599 | 5,615,099.72 | 37,797 | 3,511 |
| 27 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 108.98 | 1,173 | 4,391,020.48 | 40,292 | 3,743 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 219.61 | 2,364 | 8,447,755.52 | 38,467 | 3,574 |
| 31 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 102.98 | 1,108 | 5,284,375.06 | 51,315 | 4,767 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 81.25 | 875 | 3,580,958.46 | 44,073 | 4,095 |
| 17 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 149.35 | 1,608 | 5,865,222.88 | 39,272 | 3,648 |
| 4 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 149.79 | 1,612 | 7,448,750.64 | 49,728 | 4,620 |
| 4 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 80.7 | 869 | 3,841,359.08 | 47,600 | 4,422 |
| 3 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 110.29 | 1,187 | 4,200,000 | 38,081 | 3,538 |
| 2 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 123.22 | 1,326 | 5,004,334.53 | 40,613 | 3,773 |
| 1 May 2026 | Sales | Off-plan | Flat · 1 B/R | 81.25 | 875 | 3,464,430.97 | 42,639 | 3,961 |
| 1 May 2026 | Sales | Off-plan | Flat · 2 B/R | 152.11 | 1,637 | 7,781,428.8 | 51,157 | 4,753 |
ICONIC: common questions
Is ICONIC delayed?
Not by DLD figures. Construction was 34.86% complete at the last DLD inspection on 11 August 2026, in line with or ahead of its registered timeline (about 55% expected by then, planned completion 28 February 2028).
When is the handover of ICONIC?
The planned completion date registered with Dubai Land Department is 28 February 2028. Handover usually follows completion; the developer confirms the exact date.
How much of ICONIC is built?
Construction was 34.86% complete at the last DLD inspection on 11 August 2026, as published by Dubai Land Department.
Where is ICONIC located?
ICONIC is in Tecom Site A, Dubai.
Who is the developer of ICONIC?
ICONIC is developed by Mered Residences Real Estate L.L.C. It is registered with Dubai Land Department as project no. 2865.
Does ICONIC have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000460. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in ICONIC?
The most recent sale registered with Dubai Land Department was on 30 September 2026 for AED 7,592,382. Across the 30 recorded sales, the average was AED 3,997 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.